As we move into winter, I’d like to share an update on club operations, course developments, and upcoming projects.
Despite an exceptionally wet summer and the recent flooding caused by “Cyclone Alfred,” the golf course remains in good condition. The weather, unfortunately, forced significant disruption to daily competitions, the Club Championships, and the Keperra Bowl. Our Golf Operations team did their utmost to reallocate tee times and keep us playing, but in many instances, the weather simply prevailed.
A sincere thank you to the members who responded to the call for assistance during the clean-up effort. Your support, combined with the tireless work of our course maintenance team, played a vital role in getting the course back in play sooner than expected.
Clubhouse Refurbishment – Lower Level
Following a thorough and competitive tender process, we are now finalising the appointment of a builder to undertake the long-anticipated refurbishment of the clubhouse’s lower level. Members will be notified of the successful contractor once the agreement is finalised.
This is a major project, and as such, will bring some unavoidable disruption:
- The entire lower level will need to be vacated during construction.
- The Golf Shop will be temporarily relocated.
- Members will be required to remove all personal items from the locker rooms and buggy storage.
- Toilet facilities will be affected, and temporary arrangements will be communicated in advance.
We are targeting completion before Christmas 2025. We ask for your patience and understanding during this time. Our staff will also be working through the same disruption and will do their best to ensure a smooth transition.
We are pleased to confirm that this refurbishment will be fully funded from Club reserves. While this will draw down on our savings, our financial position remains sound.
Importantly, this project will significantly enhance member amenity and raise the profile of Keperra to a level we can all be proud of – a facility we look forward to showcasing to friends, family, and visitors.
Course Projects – Holes 7 & 8
The retaining wall on the 8th hole is entering its final stages, and construction of the green will commence on June 1st. The plan for the new green is on display in the Club Bar.
As part of our broader course improvement strategy:
- The 7th green will undergo a complete rebuild in conjunction with the work on hole 8.
- David Burrup has been appointed as the contractor for both green projects. David’s work is already well-regarded at Keperra, with recent success seen in the 16th/21st Hole Dam, Practice Fairway Redevelopment, and the recently added new tee blocks.
Constitution Review
Our Constitution Review is now underway. Information sessions and Q&A opportunities will be communicated to all members shortly. This is a vital piece of governance work to ensure our rules remain fit for purpose into the future.
In closing
The coming months will bring considerable disruption to both the clubhouse and the front nine of the course. However, the long-term benefits of these works will significantly enhance your experience at Keperra.
Once again, I encourage everyone to remain patient and supportive throughout this period. Your cooperation – and assistance, where possible – will make a big difference.
Please enjoy your golf, and as always, feel free to contact me directly should you wish to discuss any matter relating to the club.