We are pleased to confirm that the long-awaited work on Hole 8 will soon begin. Stage 1 of this important project involves replacing the retaining wall along the Kedron Brook side of the hole (the left side when playing the hole).
This project is being funded via the Queensland Reconstruction Authority (QRA) and the Department of Sport and Racing. The appointed project managers are RPS with the contractor IQ Construct. The work is scheduled to commence on Monday, 3rd February, with the program being 16 weeks.
Following the completion of Stage 1, Stage 2 will commence. Stage 2 will include the complete rebuild of the Green 8 complex. It has also been decided that Green 7 will be replaced simultaneously. The design for green 8 is displayed in the clubhouse, with the most notable change being the removal of greenside bunker. Although the design includes flood protection, the risk of flooding remains. It is anticipated that removing the bunkering will reduce future green damage, hasten reinstatement after such events and deliver economic savings.
Temporary Course Re-Configuration
As part of the upcoming work on Hole 8, the course configuration for Holes 1 to 9 will change starting 6 February 2025 (post programmed course renovation closure). Hole 8 will be removed from play, and two temporary holes, known as 5A and 5B, will be introduced to maintain the course's flow.
- Hole 5A: This will be a par 4 to a temporary green in front of the current fairway bunker on hole 5.
- Hole 5B: A temporary tee will be created in the same area as the temporary green, and play will be to the current Green 5.
The hole indexes have been reviewed in consultation with Golf Australia, and the scratch and slope ratings have been adjusted to reflect these temporary changes. These updates ensure the course provides a fair and competitive experience for all players during construction.
The Club is finalising its operational plans for replacing Green 7 and will share further details with members as soon as they are confirmed.
These improvements reflect our ongoing commitment to enhancing the golfing experience for all members and visitors. We appreciate your patience and support as we undertake these significant upgrades to the course.